IBEDC apologises, explains challenge in darkness-hit area
IBEDC’S Officer in charge of technical services, Christopher Lawal, said that a technical team had been working to back-feed the affected communities from neighbouring community with electricity supply within three weeks.
Ibadan Electricity Distribution Company (IBEDC) has apologised to customers over the state of power supply in Lalupon environs due to a collapsed bridge in the area.
The Coordinating Head, Corporate Services, Mrs. Angela Olanrewaju, said at a news conference in Ibadan on Tuesday that the collapsed bridge damaged several poles on its network.
The press conference was in response to a peaceful protest organised by some residents of the affected communities on Monday.
Olanrewaju stated that the incident had caused part of the Lalupon 33KV feeder to be isolated due to a lack of right of way to re-erect the broken poles.
This, she said, had made 32 substations out of supply, thereby affecting several communities in the area.
She reiterated the commitment of the company to resolve the main long-standing issues in the area when funds were available.
Olanrewaju said that a temporary solution would, however, be provided to restore supply to the area.
“It is part of the projects included in the Performance Improvement Projects (PIP) submitted to the Nigerian Electricity Regulatory Commission (NERC) in 2022.
“We got approval from NERC, but unfortunately we didn’t have the funding for the project, which is over N1.5 billion.
“When the CBN intervention fund in the form of loans to DISCOs came up, we decided to take advantage of that; however, the project couldn’t commence in December 2023 because CBN put the intervention fund on hold, “she said.
She also revealed that the IBEDC had commenced a quick-win solution that would ensure the supply of electricity to affected communities in the interim, pending the construction of the collapsed bridge.
“We sincerely apologise for the inconvenience, and we are using this medium to assure our customers that every effort is being made to expedite the completion of the 33 kV substation project and restore full power supply.
“As a customer-centric company, we are deeply concerned about the supply situation; as such, we have held over 10 meetings with the leaders of the communities to explain the situation.
“These meetings with community leaders underscore our commitment to resolving these issues and improving service delivery,” she said.
IBEDC's officer in charge of technical services, Christopher Lawal, said that a technical team had been working to back-feed the affected communities from neighbouring communities with electricity supply within three weeks.
“We appreciate the patience and understanding exhibited by the affected communities so far.
“We are working towards more reliable and efficient power supply for Lalupon and its environs, “he said
NAN reports that residents of the affected communities took to the streets on Monday to protest inability of IBEDC to supply electricity to them.
The protesters, in large numbers, stormed the IBEDC office and obstructed vehicular movement.